Goal of the test is to check if the Winha system fits the user requirements(usability criteria).
MB: What user requirements you mean here? The usability criteria or some other requirememnts?
...
Result of test (probably measured in %% of comletioncompletion) - 100% result OK - 0% failed
...
Then We'll discuss the results
After performing the pilot test:-
- When and where the test was executed
- The test was executed in a class(jobs), from 09:40 -10:20 ,26-11-2009
- What you have to correct in your testing plan. e.g., your task descriptions were not clear, your time estimation of how long the test takes was not correct, you did not have the right dbriefing questions, you did not get the information that you thought you would from the test.
- In our testing plan there were some questions which were unclear and open questions, so we have to make a correction there.
- Then correct your plan (state what colour you will use for the corrections so that i find them)
- . The color we used is blue.
- We made only minor changes to our plan. But about our usablity crieteria we stated six of them , but we foucused on the Efficency,Memorabilty,Errors,Satisfaction off the system. Since the user is a student and uses the winha a lot , the learnablity is a given and user in control crieteria can be included in satisfaction crieteria.
- State when and where will the actual testing take place.
- Next week(week 50).