- visiting some labels/ some artists
- get further instructions for programming and get some guidelines
- xxx
- xxx
...
week 38 (
...
22.9.2010)
Status: Describe here the current status Presentation3
...
- Continuing implementation of the prototype
- Visit in record labels
- Market research by email/interviews
- Analyzing market research
- Getting in depth to the Coding.
week 39 (26.9.2010)
Status: Describe here the current status
Prototype developement:
- Team familiar with the underlying technology/structure
- Continue on programming
- make queries
- Need to fix some bugs
Business:
- Further analyzing of risks done
- Market research sent to record labels
- Preliminary Business plan completed
- Financial plan starting
| Risks: List here the risks |
- Record labels not intrested about our service
- Overflow of users for the service
- Lack of tehcnical skills
Contingency plan: Actions to decrease the risk here
- Succesfull marketing
- Monitoring applications usage
- In case of techical problem, research
Next steps: _List here the things you’re going to do in the next week_
- Continuing implementation of the prototype
- Visit in record labels
- Market research by email/interviews
- Analyzing market research
- Getting in depth to the Coding.
week 40 (06.10.2010)
Status: Describe here the current status
Prototype developement:
- Team familiar with the underlying technology/structure
- Continue on programming
- make queries
- Need to fix some bugs
Business:
- Further analyzing of risks done
- Market research sent to record labels
- Preliminary Business plan completed
- Financial plan starting
| Risks: List here the risks |
- Record labels not intrested about our service
- Overflow of users for the service
- Lack of tehcnical skills
-
Contingency plan: Actions to decrease the risk here
- Succesfull marketing
- Monitoring applications usage
- In case of techical problem, research
Next steps: _List here the things you’re going to do in the next week_
...