Progress report
Team Aivo - Hammerkit Nokia WRT 22.9.2010
Status:
- Business plan iniated (The project manager will still have to confirm it)
- First Wireframes and mockups demonstrated on paper
Wireframes and mock-ups illustrated to steer-teachers
Feedback of the teachers considered and taken into account
Most functionality in the app scoped
Assignments for the friday determined
Risks: List here the risks
|
Contingency plan: Actions to decrease the risk here
|
Next steps:
- Coding
- Making stuff
Team Aivo - Hammerkit Nokia WRT 22.9.2010
Status:
- Research and study Nokia WRT
- Idea for the app ready
Risks: List here the risks
|
Contingency plan: Actions to decrease the risk here
|
Next steps:
- Business plan
- Designing
Team Aivo - Hammerkit Nokia WRT 9.9.2010
Status:
- Just started
Risks: List here the risks
|
Contingency plan: Actions to decrease the risk here
|
Next steps:
- Presentation for SG
- thinking and proposing ideas to app and document them
- check available apps