Report 5
Nokia Accessibility: A++, 07.10.2010
Status:
- meeting with FFVI
- Questions for user survey
- Salespitch in progress
- financials refined
- Interface refined
- programming in progress
Risks:
- Losing information (code, research materials, plans)
- Language, misunderstandings
- Financial (getting paying customers)
- Existing similar applications?
- Difficulty of the programming
Contingency plan:
- Backups
- Ask questions, make sure that we're talking about the same things
- Good marketing, apply for tekes grants
- Research
- More research, focus on the solvable problems
Next steps:
- demo ready (14.10.)
- interface final version
- implement core app
- complete sales pitch
- financilas refined
- businesscase with market strategy
- EXAM 14.10
- waiting for answeres
- plans for the 2nd periode